ODTÜ GVO - Industrial Piping Fabrication, Installation and Civil Works
- Customer
- ODTÜ Geliştirme Vakfı Eğitim Hizmetleri A.Ş.
- Location
- Çankaya/Ankara
- Project Code
- GNC_106
- Start Date
- 03.08.2026
- Completion Date
- 07.09.2026
Project Description
Within the scope of the project, the controlled dismantling and removal of the existing industrial underground piping systems that have reached the end of their service life, the execution of the necessary infrastructure preparation works, and the installation of new piping systems in accordance with the applicable project standards are being carried out. All works are performed in compliance with occupational health and safety (HSE) requirements, relevant national and international standards, and applicable quality requirements.
Scope of Work
- Dismantling and removal of the existing industrial underground piping systems
- Execution of the required excavation, infrastructure, and route preparation works
- Installation and connection of new piping systems
- Installation of supports, alignment, and mechanical assembly works
- Pressure testing, leak-tightness checks, and pre-commissioning quality inspections
- Site reinstatement and restoration of the infrastructure
With an experienced engineering team and qualified site personnel, the project is being executed with the objective of completing the works safely, in accordance with the planned work schedule, and to high quality standards. To ensure the uninterrupted continuation of training activities, all works are meticulously planned and carried out based on effective site coordination and operational planning.